Drone Thermography Case Studies — Solar Farms and Power Transmission Lines in India

Case Study 1: 50MW Solar Farm — Rajasthan

Detail Information
Client Large-scale IPP — utility scale, name confidential
Location Rajasthan, Western India
Plant size 50MW ground-mounted, crystalline silicon modules
Plant age at inspection 4 years operational
Challenge Plant generating 6.5% below P90 baseline for three consecutive months. SCADA showed no string-level alerts. IV curve tracing by O&M contractor on selected strings was inconclusive.
Elion commissioned to Identify cause and location of underperformance across the full 50MW array

 

What Elion Did

We conducted a full-array drone thermography inspection over four days in November, following post-monsoon inspection protocols. Irradiance was maintained above 650 W/m2 for all inspection days. 640×512 thermal sensor with 13mm lens, simultaneous RGB capture. The 50MW plant consists of approximately 165,000 modules arranged in 330 strings across 12 inverter zones.

What We Found

Finding Type Count Severity Estimated Generation Impact
Hotspot cells — bypass diode failures 87 modules Class 2 to 3 2.1% of total plant generation
PID — systematic string-edge pattern 14 strings across 3 inverter zones Class 2 1.8% of total plant generation
Open-circuit string faults 6 complete strings Class 3 0.9% of total plant generation
Soiling — localised bird dropping patches 234 modules Class 1 0.4% of total plant generation
Delamination — early stage 12 modules Class 1 Negligible current impact, monitor
TOTAL estimated generation loss All findings combined Mixed Approximately 5.2% of total plant generation

 

Result

The O&M contractor replaced the 87 modules with bypass diode failures, cleaned the 234 soiled modules, repaired the 6 open-circuit string faults (5 failed string fuses, 1 loose MC4 connector), and initiated a grounding review to address PID across the three affected inverter zones.

Post-repair generation monitoring showed a 5.1% improvement in plant output relative to the pre-inspection baseline — recovering approximately INR 2.4 crores per year in additional generation revenue at a tariff of INR 2.85 per unit. The Elion inspection cost was recovered from the first month of improved generation.

 

Case Study 2: 220km Transmission Corridor — Central India

Detail Information
Client State Transmission Corporation — name confidential
Location Central India — mixed terrain including flat and forested sections
Line details 220kV double circuit, approximately 220km corridor, 440 towers
Line age 18 years operational
Challenge Two unexplained circuit trips in 6 months. Ground patrol completed but no visible cause found. Client needed to identify thermal anomalies before the summer demand peak.
Elion commissioned to Complete full corridor drone thermography and identify all thermal anomalies above 5 degrees delta-T

 

What Elion Did

We deployed two drone units simultaneously on different sections of the corridor to complete the 220km inspection in 8 days. NOTAM filed with AAI for three sections near aerodromes along the corridor. Coordination with state utility load dispatch centre to freeze switching operations during each day’s inspection window. 640×512 thermal sensor with 25mm telephoto lens, maintained 30-metre standoff from live conductors throughout.

What We Found

Finding Type Count Severity Towers Affected
Splice joint overheating delta-T above 10 degrees 43 locations Class 2 to 3 Distributed across 38 towers
Splice joint critical delta-T above 20 degrees 8 locations Class 3 — urgent 8 towers — recommended emergency outage
Clamp and hardware hotspots 27 locations Class 2 22 towers
Insulator string thermal anomalies 15 strings Class 1 to 2 12 towers
Earth wire conductor breaks thermal signature 4 locations Class 2 4 towers — visible in RGB also
Vegetation encroachment — thermal contrast mapping 11 spans Operational risk Flagged for ROW clearance team

 

Result

The 8 critical splice joints were replaced in an emergency outage coordinated with the state load dispatch centre within 3 weeks of report delivery. Post-repair thermal imaging was conducted on the repaired sections to confirm normal operating temperature. The remaining Class 2 findings were incorporated into the utility’s 12-month planned maintenance schedule.

No further circuit trips occurred in the 12 months following the inspection and repairs. The utility has since commissioned Elion for annual inspection of this corridor.